The new-home schedule in wall-framing-takeoff counted Monday to Friday and nothing else, so a build that crossed July 4 or Thanksgiving finished a day or two earlier on paper than on site. The plan's schedule object now takes two optional lists of dates, holidays and weatherDays (YYYY-MM-DD). Those days are skipped like weekends: a three-day job starting Monday March 2 with a Tuesday holiday finishes Thursday March 5.
Nothing is shipped: you type the dates your crew will not work. Weather is not forecast, and working-day counts and the critical path are unchanged; only the calendar dates move. It is checked by hand-worked cases in schedule.test.mjs, including a holiday on the start date and one on a weekend. There is no page field yet; use the JSON box or the CLI (--schedule).