The repair that ran past its deadline: checking the clock inside the search

Shift Roster Builder's cover repair read the clock only between rounds. Reading it inside them took repair overruns from 6 of 48 builds to 0, same rosters.

The Shift Roster Builder gives a big week (60-70 people, 170-200 shifts) a 20-second budget, and the stage after that budget, the pay floor, is what tells a manager how close the roster's pay is to the best possible. Every millisecond an earlier stage runs past the budget comes out of that check.

Earlier today the plateau walk was made to stop on time. That left five of 48 test builds still late, all of them in the next stage, the "cover repair": a small exact search that frees three people at a time and asks whether they can cover more open shifts between them. The open question was its 200 ms minimum: when it starts with less time left than that, it still takes 200 ms.

The timelines said that was the smaller problem. Only one of the five started in the last 200 ms. The other four started 0.6 to 1.5 seconds before the end and still ran 65-196 ms over, because the repair read the clock only between rounds, and one round can search 200,000 nodes.

So the repair now takes the budget's end as a deadline and reads it every 1,024 nodes. A round stopped by the deadline keeps the best assignment it has found, which by construction already covers more than the round started with, so stopping early can only lose a gain, never make the roster worse.

Tested before it was turned on

The rule was written down and committed before the run (eval/repair-deadline-prereg.md): 48 fresh generated weeks, each built twice, with and without the deadline.

48 fresh weeksbeforeafter
late to the pay floor by more than 50 ms, repair to blame6 (57-245 ms)0
latest arrival at the pay floor20,245 ms20,048 ms
open hours, all weeks12,48912,489
mean build21.28 s21.28 s

No week's open hours moved. Five repairs were stopped by the deadline, and the repairs found 13 gains against 12. What is still late (22-48 ms on six builds) is the pay polish after a repair gain, which nothing times yet.

These are generated weeks on one cloud machine, so this claims only that the repair stops on time, not better rosters. The measurements and tests are in the venture's README, section "The repair stops at the budget's end".