XER Schedule Check reads Microsoft Project schedules saved as XML (MSPDI) as well as Primavera P6 .xer files. It recomputes every task's dates and float and checks them against what Project stored. On the 102 Project files in MPXJ's public test data it matched 2,442 of 2,491 open tasks this morning. Two of the misses had the same label in our notes: "split tasks, not modelled."
What a split is
In Project you can split a task: cut it, drag the second half to the right, and leave a gap with no work in it. Planners use it when a crew leaves a job and comes back, for example while concrete cures or an inspection waits. The task keeps its duration (80 hours of work is still 80 hours). Its finish, though, moves out by the length of the gap.
A checker that ignores the gap gets the finish wrong. On the test file mspdisplittask.xml the old reading put the project finish a week early, on 11 October 2006 instead of 18 October.
Where the gap is stored
The XML has no split field on the task. A task says only Start 2006-09-21, Finish 2006-10-09, Duration 80 h. Count the working hours between those dates and you get 104. The missing 24 hours are in the assignment's timephased rows: one row per day of remaining work (Type 1), with the value PT8H0M0S on a working day and PT0H0M0S on a day inside the split. Weekend rows carry no value at all, so a row with no value is time off, and a row with a value of zero is a split.
The rule
The reader now collects, for each task, the zero-work rows of all its assignments. It keeps only the stretches that sit between the task's first and last work, and only where no other assignment of the same task is working (one person off while another works is not a split). The working time in those stretches is added to the task's span in both the forward and backward pass.
Two details matter in practice:
- A split moves with the task. If a new predecessor pushes the task a day later, the split keeps its length in working hours and moves with it. It does not stay pinned to its old dates. Project behaves the same way when it reschedules.
- Splits already behind a task in progress add nothing. Only the part after the task's Resume date (or the status date) counts.
The result
| before | after | |
|---|---|---|
| open tasks matching Project on early finish, late finish and float | 2,442 | 2,446 of 2,491 |
| early finish alone | 2,483 | 2,490 |
The corpus has seven split tasks, and the reader finds every one: the two in mspdisplittask.xml and five variants of one task in mspditimephased.xml (day shift, night shift, 24 hours, 50% and 150% units). That second file had been listed as "contoured work". It turns out its five early-finish misses were splits too. All seven now finish where Project says. The other 100 files read exactly as before, line for line.
Converting to P6 is the catch. P6 has no splits, so an XER written from a Project file with split tasks loses them. The tool's warnings now say so and count the split tasks.
What is still open
The remaining 45 misses are mostly late dates in two timephased test files, which no logic rule we know of explains. The bigger gap is that these are small test projects. A real construction schedule with split tasks, saved from Project, has not been through the reader yet. The full measurement is in eval/split-tasks-2026-11-21.md. The tool is free, runs in the browser and uploads nothing.