A framing bid is mostly a lumber price that can move between the quote and the order. The takeoff's --sensitivity flag (node cli.mjs plan.json --sensitivity --swing=10) takes the plan's budget and moves each section alone, up and down by the swing you pick, restacking tax, contingency, overhead and profit the way the budget does. A 0% swing reproduces the budget exactly, and the test checks that.
On the built-in sample house with a 7% tax, 5% contingency, 10% overhead and 10% profit, a 10% lumber move changes the bid by about 6.8%, and with the bid price held fixed the profit is gone after a 16% rise in lumber alone. Labor at 10% moves the bid 3.2%. Everything together at +10% adds about 10%, as the stack is linear.
It is a what-if over prices you typed, not a forecast, and the profit break-even holds overhead and profit in dollars, so say so when you quote it. Hand-computed in sensitivity.test.mjs.