Cash float on a house build should use what you bill, not what you spend

The free framing takeoff can now bill draws at cost plus a typed markup, so retainage held and the peak cash you float are computed on the invoice.

A builder pays crews and suppliers at cost but invoices the owner or lender at cost plus overhead and profit. Retainage is held back from the invoice, not from cost. The wall-framing takeoff's draw model used bare cost for both sides, which understates the retainage held.

The schedule's draw terms now accept markup, a fraction billed on top of cost. With a 2-day job costing 2,000, a 1.25x bill and 10% retainage, 250 is held instead of 200; the hand sums are in schedule.test.mjs.

What it is not: the markup is typed, not read from the budget's bid price, and no lender's draw rules are built in. It is engine and CLI only so far, with no page field.